Plumbing rough-in begins, electrical continues

While Katie did some final tweaking on the electrical box rough-ins in the upstairs bedrooms, including the smoke detector boxes, I started in on the water supply plumbing roughins. The grand strategy in all this is to get all the locations fixed so that we know where to drill all the holes.  (I purchased all the supplies and tools for expansion PEX over the Christmas holiday.)

Downstairs bathroom sink

Downstairs bathroom toilet

Basement wet bar sink

Laundry room washer shutoff and drain

Main level toilet room

I'm take the week of July 4th off work to drill holes and run PEX and wires. 