Finally received our certifiate of occupancy Friday morning.
KnArrow Haus's long-awaited Certificate of Occupancy
It was a bit of an ordeal to finally pass inspection. I scheduled both inspections, the electrical and the county's building inspection on Tuesday. Only the county showed up on Tuesday. L&U showed up Wednesday, but thankfully passed us without anyone there.
The county inspector asked me to resolve 4 items, and said if I would email pictures of the corrections, he would go ahead an issue the certificate:
-  The ends of the downstairs railings needed to terminate in to the wall.

 - I was missing one switch plate cover.
 - I needed to install the inside ventilation covers in the toilet rooms, showers, and utility room.
 - And we're required to have 4" high house numbers visible from the street. (These are definitely temporary -- I'll do something more stylistically in keeping in the spring.)
 
On Monday evening, we also completed the bunk bathroom light fixture:
Later Monday evening, while wiping down the shower I threw-out my lower back. Got to the chiropractor on Wednesday, and then promptly threw it out *again* Thursday evening. A fitting end to a week of passed inspections.  I'm convalescing my back this weekend as snow pours down in the passes.
Even though we've passed the legally required inspections, we still have a fair amount of work to do. 
- Hook-up the range and dishwasher
 - Hook-up bathroom sink drains, which will require turning some cabinet drawers into cabinet doors.
 - Install floating shelves in the kitchen and kitchenette
 - Backsplashes for the range and bathroom sinks
 - Caulk the baseboards on all three floors
 - Touch-up paint on all the walls
 - Hang the barn doors for the top floor bathrooms
 - Bathroom mirrors and shelves
 - Install a few more door handles
 - Paint front and back doors.
 - Fireplace mantel
 