A beautiful, bluebird day for working on KnArrow Haus doing what can only be characterized as the endgame.
starting early afternoon, even though we have daylight until early evening.
Started off the workday with a gimme: Installing the microwave. We've been using a cheapo-temp microwave during construction that will now be relegated to the basement. I searched high and low, long and hard to find a black stainless steel that was 18" wide or narrower. They don't exist. This LG model that is _exactly_ 18" wide and has a 1000 watts of power.
The next order of business was far less glamorous. I applied another coat of epoxy to the drain trough and pipe flange in the bunk bathroom sink -- don't want to take any chances with it leaking (again) after my first failed attempt at repair. (Really annoyed that a sink that expensive wasn't perfect out of the box.)
Sorry, no pics.
With Katie's help, I mounted the sliding door track for the bunk bathroom.
I did a lot of measuring, planning, and remeasuring to make sure the wheels on the track would clear the perpendicular vent pipe; and so the door would also be at the right height for the opening. Not too high. Not too low. Just right.
Because the framing is a little off inside the wall and the track crossed the opening at the top of the doorway, I had to drill an extra hole in the metal track. But I'm good at drilling through metal after my experience with the stair railing.
With both sliding door mounted the next order of business was installing the handles.
...still laughing about licking the frozen pipe railing!